Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, APRIL 27, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor completed laying CMU block in the Tiger Room, and continued the block work in the corridor and restroom along the MEB loading dock.
  • Workers started roughing in the electrical in the CMU block walls along Gravier Street.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor covered the new underground electrical conduits with concrete near the electrical utility chase.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits for emergency power.

LIONS/LSU CLINIC 7th FLOOR LAB RENOVATIONS:

  • The contractor installed fire alarm strobes, the final three light fixtures and continued installing ceiling tiles.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATION:

  • The contractor began running conduit for the A/V equipment in the large conference room.

LANDSCAPING/EXTERIOR:

  • Facility Services continued grading and removing roots on the parking lot side of the School of Dentistry Clinic Building.