MONDAY, APRIL 5, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor installed sewer and water lines for the 1st Floor restrooms on the Gravier Street side of the building. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor back-filled around the pile caps. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor created 3 floor penetrations in the Automatic Transfer Switch room and ran conduit through 2 of the new penetrations. LIONS/LSU CLINIC 7th FLOOR RENOVATIONS: · The contractor started installing the lab furniture along the Gravier St. side of the lab. CEB COVERED WALKWAY: · The contractor continued removing the old sidewalks near 1542 Tulane Ave. EXTERIOR/LANDSCAPING: · Facility Services continued planting shrubs and plants in the patio courtyard and pressure washed the sidewalks. |