WEDNESDAY, MAY 12, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued to insulate and install studs over the windows along Bolivar Street. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor continued installing underground conduit and piping. · They ran electrical conduit from the underground trench to the Entergy vault. LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS: · The contractor continued to work on punch list items. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor relocated sprinkler heads and ran conduit in the large conference room. LANDSCAPING/EXTERIOR: · Facility Services completed planting shrubs on the Florida Avenue side and the parking lot side of the School of Dentistry Clinic Building. |