Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MAY 21, 2010

 

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor installed two additional cross braces for the auditorium structural steel.  Five of twelve cross braces have been put in place.  

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor removed additional sand fill in preparation for the stone base course.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor completed the remaining floor penetrations in the 2nd Floor pump room.

·         Crews continued running conduit from the 1st Floor emergency circuits to the 2nd Floor ATS room.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The contractor rerouted ductwork for the Liebert unit.

 

CEB COVERED WALKWAY:

·         The contractor continued asbestos abatement of the active steam lines.

 

LANDSCAPING/EXTERIOR:

·         Facility Services completed installing irrigation piping on the field side of the horseshoe drive at the School of Dentistry.