Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, MAY 26, 2010

 

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor finished installing the structural steel for the new auditorium on the 2nd Floor.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor continued compacting fill at the base of new building.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor continued flood proofing the pits for Elevator 3 & 4.

·         Sheet rock was hung in the new ATS room on the 2nd Floor.

·         Workers continued cleaning the granite on the south and east side of the building.

 

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

·         The contractor installed wiring raceway.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The contractor continued to patch the walls in the small and large conference rooms and the Directors office.

·         They continued repairing the ceiling grid near the lounge and restrooms.

 

CEB COVERED WALKWAY:

·         The contractor completed the asbestos abatement of the active steam lines.

 

LANDSCAPING/EXTERIOR:

·         Facility Services installed sod on the parking lot side of the Clinic Building and field side of the horseshoe drive at the School of Dentistry.