WEDNESDAY, MAY 5, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor delivered structural steel to the site. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor began running conduit and wire for the floor outlet in the main lobby on the 1st Floor. · They continued installing electrical conduits for emergency power. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor erected the concrete forms around the rebar cages for the 12 support columns. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor performed final clean up. The project is substantially complete. LANDSCAPING/EXTERIOR: · Facility Services continued placing and grading topsoil on the Florida Avenue side of the School of Dentistry Clinic Building in the section between the sidewalk and the street. |