FRIDAY, MAY 7, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor started laying out the structural steel supports and adjusted sprinkler heads on the 1st Floor. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor poured concrete for all 12 structural columns from grade to the 2nd Floor deck. LANDSCAPING/EXTERIOR: · Facility Services completed placing and grading topsoil on the parking lot side of the School of Dentistry Clinic Building. |