FRIDAY, JUNE 11, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor removed the stairwell walls in the two stairwells near South Roman Street.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued forming the 2nd Floor and began placing reinforcing steel in the forms.
  • Crews completed the second trench across the main driveway of the Residence Hall parking lot.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued construction of the CMU walls in the office areas and in the Womens restroom.
  • They completed the CMU walls in the Mens restroom.
  • Crews began installing the elevator pit equipment for Elevators 3 and 4.
  • The contractor created 2 of 7 floor penetrations that are needed in the new switchgear room.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor completed installing the light pole electrical service conduit and backfilled the trenches.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued roughing in light fixtures for the large conference room.
  • The glass was installed in the large conference room doors.