Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JUNE 17, 2010

ALLIED HEALTH/NURSING BLED PERMANENT REPAIRS & MITIGATION:

  • The contractor installed additional CMU in the stairwell at the corner of Gravier and S. Roman streets.
  • Crews laid six new CMU block walls for office area on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued trenching near the C tower storage room on the Bolivar Street side for the plumbing.
  • The forms were removed from the 2nd Floor columns.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • 16 of 25 conduits have been installed in the switchgear room.
  • The contractor is fabricating the chilled water bypass piping in the 2nd Floor pump room.
  • They continued to install the elevator pit parts for Elevator 3 and 4.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued the preparation of the base course and hauling away the excavated material.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued installing the ceiling tiles in the large conference room.
  • The wood floors in the Directors Office have been installed.

CEB COVERED WALKWAY:

  • The contractor continued to drive piles.