Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JUNE 18, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor installed additional CMU block in the stairwell at the corner of Gravier and S. Roman streets.
  • Crews continued to run fire alarm cables to the 2nd Floor fire alarm panel.
  • The contractor continued installing six new CMU block walls in the office area on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed underground plumbing near the C Tower storage room on Bolivar Street side.
  • Workers started building concrete forms for the roof of the new enclosure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor removed the exterior wall of the new switchgear room.
  • They continue to install the elevator pit parts for Elevators 3 and 4.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued to prepare the base course.
  • They completed hauling away the excavated material.
  • Crews started installing the geo-textile fabric and laying limestone base material.

CEB COVERED WALKWAY:

  • The contractor continued to drive piles. 10 piles remain to be driven.