WEDNESDAY, JUNE 23, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continues to run fire alarm cables to the 2nd Floor fire alarm panel.
- Workers continue installing CMU walls on the 1st Floor.
- They continue to form up the elevator wall.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed underground electrical conduit near the C Tower storage room on the Bolivar Street side.
- Crews continue to build the concrete forms for the roof of the enclosure.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued to install the elevator pit parts for Elevators 3 and 4.
- The concrete pad for the electrical transformer has been placed in the ATS room.
- Workers continue to weld the chilled water bypass piping in the 2nd Floor pump room.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor continued installing geotextile fabric and spreading the limestone base material.
LIOHNS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor laid floor tile in the elevator lobby and glass tile on the reception area walls.