FRIDAY, JUNE 25, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continues to run fire alarm cables to the 2nd Floor fire alarm panel.
- Concrete for the elevator shaft wall was poured.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor core drilled in the grade beam for plumbing near the C Tower storage room on the Bolivar Street side.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continues to install the elevator pit parts for Elevators 3 and 4.
- A CMU wall was constructed in the new switchgear room on the 2nd Floor.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor continues laying floor tiles in the elevator lobby and began grouting the new tiles.