MONDAY, JUNE 28, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued to run fire alarm cables to the 2nd Floor fire alarm panel.
- Workers removed the ceiling grid and wall paper from the 2nd Floor corridor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor completed core drilling in the grade beam for plumbing near the C Tower storage room on the Bolivar Street side.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor installed the housing for 1 of the 2 electrical panels in the 2nd Floor switchgear room.
- They formed the housekeeping pads for the switchgear.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor began installing the concrete curbs.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor installed VCT in the break and mail room.
- They started installing carpet tile in the large conference room.
- Workers pulled wires for the dimmer panel in the mechanical room.
CEB COVERED WALKWAY:
- The contractor finished driving the piles that will support the walkway.