WEDNESDAY, JULY 14, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The general contractor applied the 5th and final coat of fire proofing to the structural steel beams.
- The contractor re-installed the granite panels surrounding the elevator lobby.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The mechanical contractor poured the concrete pad for the AHU in the 1st Floor mechanical room.
- The contractor ran electrical conduit in the 8th Floor electrical room.
- Crews laid CMU block for Elevators 1 & 2 on the 1st Floor.
- The roofing contractor began erecting roof curbs for the emergency generator.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing the new electrical duct bank in the main driveway.
- The contractor continued installing steel reinforcement in the concrete forms for the roof of the new enclosure.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor began laying the asphalt paving and completed the base course.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor continued painting walls.