THURSDAY, JULY 15, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing granite panels surrounding the elevator lobby.
- The elevator sub-contractor started installing pit parts for Elevators 1-3.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing electrical conduit in the 8th Floor electrical room.
- The general contractor constructed the temporary shaft wall for Elevators 1 & 2 on the 1st Floor.
- The roofing contractor continued erecting the roof curbs for the emergency generator.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing the new electrical duct bank in the main driveway.
- The concrete for the roof of the new enclosure was poured.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor completed laying the wearing course on the parking lot.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor finished installing the lighting dimmer panel.
- The AV contractor installed the projection screen in the large conference room.