Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JULY 27, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued rewiring the electrical panels in the 1st Floor electrical room.
  • Metal wall studs were removed from Rooms 218 and 219.
  • The fire panel has been relocated to the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running electrical conduit on the 8th Floor.
  • The contractor began penetrating the roof deck for the electrical conduit that will serve the roof mounted emergency generator.
  • The mechanical contractor continued to set the 1st Floor AHUs.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor finished removing the concrete forms from the new elevated enclosure.
  • Workers began roughing in the plumbing for the 2nd level of enclosure.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor compacted the sub-base for the new driveway and surveyed for the new sidewalks.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor core drilled for the podium.