ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued rewiring the electrical panels in the 1st Floor electrical room.
  • Crews continued removing metal wall studs and floor tiles from Rooms 214, 218 and 219.
  • They continued removing the heating hot water pumps from the 2nd Floor mechanical room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed CMU shaft walls for Elevators 1 & 2 on the 1st Floor.
  • They removed the access panels on the supply duct on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued the electrical rough-in for the 2nd level of the new elevated enclosure.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor built the forms and poured concrete for the curbing along all of the new sidewalks.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • Facility Services installed the sink in the break room.
  • The contractor started installing the crash rails.