Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JULY 7, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to run conduit and installed electrical panel D1A.
  • They continued cleaning the CMU wall for Elevators 1, 2, and 3 on the 1st Floor.
  • Crews began fire proofing the structural steel beams.
  • The sump pump waste line serving the elevator put was run.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit in the 1st Floor ceiling for the electrical panels on the 2nd Floor.
  • The breakers in two electrical panels in the 2nd Floor switchgear room were installed.
  • Workers began insulating the chilled water piping in the 2nd Floor pump room.
  • The contractor removed one of four air handling units from the 1st Floor mechanical room in preparation for raising the unit.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 30 additional feet of electrical conduit, installed a 6-inch roof drain piping in the main driveway, and back-filled the area.
  • Crews continued building the concrete forms for the roof of the new addition.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued forming up and pouring concrete curbs and islands.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor completed installing light shades in the elevator lobby and the Directors office.
  • They completed the ceiling tile installation in the Directors office
  • The contractor started installing wall paper and wood baseboard.