Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JULY 9, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to run conduit and work to complete the installation of electrical panel D1A.
  • Crews applied the 3rd coat of waterproofing for the elevators.
  • The 2nd of 5 coats of fire proofing were applied to the structural steel beams.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued pulling wires in the new switchgear room on the 2nd floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor removed concrete near the A Tower electrical room on the 1st Floor.
  • The cleaned the parking area underneath the basketball court.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued to install protective bollards and graded the parking area.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued installing wall paper, wood baseboard and millwork throughout the renovated space.
  • Workers painted the elevator soffit.