FRIDAY, JULY 9, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued to run conduit and work to complete the installation of electrical panel D1A.
- Crews applied the 3rd coat of waterproofing for the elevators.
- The 2nd of 5 coats of fire proofing were applied to the structural steel beams.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued pulling wires in the new switchgear room on the 2nd floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor removed concrete near the A Tower electrical room on the 1st Floor.
- The cleaned the parking area underneath the basketball court.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor continued to install protective bollards and graded the parking area.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor continued installing wall paper, wood baseboard and millwork throughout the renovated space.
- Workers painted the elevator soffit.