WEDNESDAY, AUGUST 11, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued removing elevator pit parts.
- Crews continued removing the heat exchanger.
- Duct work was removed from the 2nd Floor.
- The contractor installed the CMU in the Tiger Room.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor removed insulation from the existing chilled water lines in the 2nd Floor pump room.
- Workers are cleaning the 1st Floor AHUs.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed 3 additional precast panels on the 2nd level of the elevated enclosure.
- 19 of the 40 panels have now been installed.
LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:
- The contractor installed access control wire in the large conference room.