FRIDAY, AUGUST 13, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor began removing the elevator shaft wall.
- The heat exchanger has been removed.
- Workers continued welding new heating hot water lines.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed 4 additional precast panels on the 2nd Floor and roof level of the elevated mechanical/electrical enclosure.
- 23 of the 40 panels are now in place.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued to remove paint from the 1st Floor walls.
- Crews continued to torque the bus duct in the switchgear room.
- The granite thresholds for Elevators 1 and 2 were installed.
LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:
- The contractor continued installing access control wire in the large conference room.