THURSDAY, AUGUST 19, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor started installing the metal lath for the stucco walls in the Tiger Room.
- Workers poured concrete for the elevator shaft wall.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed 2 additional precast panels on the 2nd Floor of the elevated structure,
- 38 panels have now been installed and 2 remain.
- Crews installed electrical conduits on the 2nd Floor.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor began painting the 1st Floor walls.
- They continued to remove chilled water pipe from the 2nd Floor pump room.
- The contractor continued installing the pit parts for Elevators 1 & 2.
|