Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 25, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing the metal lathe for the stucco walls in the Tiger Room.
  • The contractor continued welding connections for the chilled water lines on the 2nd Floor.
  • Supports were installed for the 10 storefronts that have been put in place.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor built forms for the concrete pads for the pumps that will be installed in the 2nd Floor pump room in the enclosure.
  • Crews continued installing the steel tube platform on the roof level of the enclosure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing bus duct in the new 2nd Floor switch gear room.
  • Fire sprinklers were relocated in the 2nd Floor switchgear room.
  • Workers continued painting the 1st Floor walls.

CEB COVERED WALKWAY:

  • The contractor continued fabricating the rebar for the footers and setting the forms for the walkway.