MONDAY, AUGUST 9, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor removed the digital sign and granite panels from the 1st Floor elevator lobby.
- The elevator pit parts were removed.
- Crews continued removing the heat exchanger and relocating the pneumatic panel to the new mechanical room on the 2nd Floor.
- Door frames were installed in the Tiger Room, and the 1st Floor bathrooms.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor set one of five cabinets for the new switchgear in place.
- Two temperature sensors and one flow meter for the chill water lines were relocated in the 2nd Floor pump room.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed 5 additional precast panels on the elevated enclosure.
- Twelve of the forty panels have been installed.
LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:
- The contractor installed additional fire alarm devices in the renovated spaces.