Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, SEPTEMBER 21, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor installed expansion joints and corner beads throughout the 1st Floor space.       
  • The contractor continued making fittings and installing new heating hot and chill water lines.  5 of 12 heating hot water taps were made for the new VAV boxes.
  • The contractor continued installing elevator pit parts for the freight elevator. 
  • Workers continued removing additional red metal panels along the walkway bridge.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing conduits on the 2nd Floor of the elevated structure.
  • The contractor continued cleaning the exterior wall surface of the storage area by the C tower.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor set the door frames for Rooms 153, 155, and 158.
  • Elevators 2 & 3 were released for normal operation.
  • The contractor continued installing the granite panels in the 1st Floor elevator lobby.

CEB COVERED WALKWAY:

  • The contractor set 23 8-ft steel columns and 2 10-ft steel columns for the walkway section near the 1542 canopy. 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The project passed the State Fire Marshall Inspection.