FRIDAY, SEPTEMBER 24, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The masonry contractor installed additional expansion joints and corner beads throughout the 1st Floor space.
- The contractor insulated the new chilled water lines along the walkway.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing conduits on the 2nd Floor of the elevated structure.
- The contractor ran domestic water lines from the mechanical chase to the pump.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor completed re-installing the granite panels on the 1st Floor.
- The door frame was set in Room 125B.