CEB COVERED WALKWAY:

  • The contractor set rebar for the walkway footers at the Claiborne Avenue entrance to the District Entergy parking structure.
  • Crews set anchor bolts for the footers that run along the District Entergy garage.

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
  • Workers continued making fittings for the chilled water and heating hot water lines.
  • Crews applied the first of two anti-microbial duct coatings to the VAV boxes.
  • The contractor applied the first of two waterproofing coats to the elevator shaft walls.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed steel reinforcement for the elevator shaft wall in the elevator pit.
  • They continued to prime walls in the mail room.
  • The electrical contractor continued terminating wiring in the switchgear.