MONDAY, OCTOBER 18, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued applying the 3rd coat of stucco to the interior office space on the 1st Floor.
- Additional heating hot water lines are being installed on the 2nd Floor.
- The contractor continued demolition of selected 2nd Floor office areas.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor continued placing the cap sheet layer of the roof on the new building.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing the metal lathe on the walls in the Womens restroom.
- Crews continued to remove chilled water piping from the 2nd Floor pump room.
- The contractor replaced the 1st Floor windows and refinished the window frames on the Bolivar Street side of the building near Gravier Street.