Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 2, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued ran heating hot water lines to the heating hot water pumps. 
  • Crews continued the demolition of the 2nd Floor AHUs.
  • CMU block was laid to complete the wall around the installed ductwork along Bolivar Street.
  • The contractor placed the first coat of stucco in Stairwell D.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractors continued installing the exhaust pipe for the emergency generator.
  • They continued connecting the electrical conduit to the new switchgear. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed one of two doorframes and a block wall in the new switchgear room.