TUESDAY, NOVEMBER 2, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued ran heating hot water lines to the heating hot water pumps.
- Crews continued the demolition of the 2nd Floor AHUs.
- CMU block was laid to complete the wall around the installed ductwork along Bolivar Street.
- The contractor placed the first coat of stucco in Stairwell D.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractors continued installing the exhaust pipe for the emergency generator.
- They continued connecting the electrical conduit to the new switchgear.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor installed one of two doorframes and a block wall in the new switchgear room.