Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 23, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor ran control wiring for the differential pressure sensor on the 9th Floor and the VFD installer started up the units. 
  • The contractor installed more sheet rock along the MEB side of the auditorium, set electrical receptacles and installed studs for the mechanical room behind the auditorium. 
  • Workers demolished the remaining offices along Gravier Street. 

RESIDENCE HALL MITIGATION

  • The contractor continued terminating electrical wires at the ATS on the 2nd Floor.

RESOURCE CENTER MITIGATION

  • The contractor installed the base plates for the generator platform on the roof.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor removed light fixtures from the transformer vault in the basement.

CEB COVERED WALKWAY:

  • Crews continued installing reinforcing steel for the walkway connecting to the canopy closest to the Clinical Education Building.
  • They continued building formwork for the two staircases.

ELEVATED WALKWAY RESURFACING:

  • The contractor applied primer and leveling filler on the Lions/LSU Clinics Building and CSRB connecting bridges.