Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 30, 2010

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor ran electrical conduits in the basement to reroute panel X1LP1 to Room 134 on the 1st Floor.

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for electrical receptacles around the perimeter of the auditorium. 
  • The demo contractor continued removing the remaining metal studs and electrical conduit from the remaining offices along Gravier Street. 
  • The mechanical contractor continued installing ductwork in the 2nd Floor auditorium and installed temperature sensors for the heating hot water lines. 

CSRB EXHAUST PROJECT:

  • The contractor re-routed fire alarm and building controls around the temporary ductwork on the 2nd Floor. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel lines on the 1st Floor.