Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, NOVEMBER 4, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued running heating hot water lines to the heating hot water pumps. 
  • Workers continued the demolition of the 2nd Floor AHUs.
  • The second and third coats of stucco were applied to the walls in Stairwell D.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the fuel line for the fire pump.
  • Electricians continued connecting the electrical conduit to the new switchgear and the ATS.
  • A CMU block wall was laid for the domestic water pump room. 

CEB COVERED WALKWAY:

  • The contractor completed installing the curved roof supports leading up to the canopy adjacent to the District Energy Garage.
  • They continued building formwork for the grade beams at the canopy closest to the Clinical Education Building.