Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, DECEMBER 1, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for the receptacles on the perimeter of the auditoriums. 
  • The demolition contractor continued removing the remaining metal studs and electrical conduit from the offices along Gravier Street. 
  • The mechanical contractor continued installing ductwork in the 2nd Floor auditorium and installed temperature sensors for the heating hot water lines. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued terminating wires at the switch gear on the 2nd level.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued relocating conduits in the basement to reroute panel X1LP2 to the Room 134 on the 1st Floor.

CEB COVERED WALKWAY:

  • The contractor completed erecting steel columns and joists for the section of walkway adjacent to the Clinical Education Building.

CSRB EXHAUST PROJECT:

  • The contractor installed the temporary duct riser on the 1st three floors of the building floors.

DENTAL CAMPUS ROAD REPAIRS:

  • A project to make repairs to the entrance and exit driveways on the Dental School campus has begun.
  • The contractor demolished the existing concrete driveway at Army Boulevard.