Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, DECEMBER 6, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for receptacles surrounding the auditoriums.
  • They installed light fixtures in mechanical room 246. 
  • The mechanical contractor continued installing ductwork in the 2nd Floor auditorium and along Gravier Street on the 1st Floor. 
  • Crews also ran copper piping for the compressed air line re-location.
  • The contractor continued to correct the stucco punch list items on the 1st Floor.  
  • There will be a compressed air shutdown Tuesday morning to re-locate the pneumatic air line outside of the auditorium.  The air will be turned on by 6:00 AM and there will be no impact to building occupants.  

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor finished laying the asphalt in the main driveway.
  • Light fixtures are being installed in the elevated structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the legs to the emergency generator platform that is located on the roof.

CEB COVERED WALKWAY:

  • The contractor continued constructing the concrete forms for the steps leading to the back side of building.
  • They continued welding the steel canopy supports in place for the walkway roof near the CEB.

DENTAL SCHOOL CAMPUS ROAD REPAIRS:

  • The contractor installed concrete forms at the entrance to Army Blvd and base course material at the exit for Navy Blvd.