Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JANUARY 10, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor installed AV and electrical conduit in the wall and along the floor for the Tiger Room and Room 138.
  • The contractor continued to address the stucco punch list items.   

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor welded the walkway grating on the generator platform.
  • Workers began finishing the ceiling in the 1st Floor elevator lobby.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor began demolishing the roof of the transformer vault near the loading dock.

CEB COVERED WALKWAY:

  • The contractor continued welding the tapered supports for the canopy covering the entrance to the Clinic Education Building.

CSRB EXHAUST UPGRADE:

  • The contractor relocated conduit in the 4th, 5th and 6th Floor mechanical rooms.
  • Crews installed duct work in the 2nd Floor mechanical room.
  • They rerouted the de-ionized water piping on the 1st Floor. 

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor poured concrete for two AHU foundation pads (above the gross anatomy and oral pathology labs).
  • The 3" heating hot water riser for the penthouse was fabricated. 

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor replaced 31 additional light fixtures on the 8th Floor of the Clinic Building along the horseshoe side of the building.