FRIDAY, JANUARY 14, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • Workers continue to correct items on the stucco punch list.
  • Additional metal studs were installed for the birthing labs on the 2nd Floor.
  • The contractor installed more sheetrock on the exterior of the auditorium along Perdido Street. 
  • The floor in the Tiger Room was patched.
  • The contractor set the generator in the old switchgear room. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor terminated six feeder cables at the new switchgear.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • Workers are painting the 1st Floor mail room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor removed exterior sprinkler pipe in the loading dock.
  • They removed brick pavers from in front of the loading dock area.

CSRB EXHAUST UPGRADE:

  • The contractor lifted the exhaust ductwork on the 1st Floor into place and connected all of the branch lines.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued fabricating the 3 inch heating hot water riser for the penthouse.
  • They fabricated the manifold system for the AHUs above the Gross Anatomy and Oral Pathology labs.   
  • The contractor delivered air handling units 3A and 6A.

DENTAL SCHOOL STUDENT RECREATIONAL FIELDS:

  • The contractor surveyed and marked control points for the sports fields.