Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, FEBRUARY 17, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the ceiling grid in the 1st Floor office area.   
  • Crews continued framing the entryway furdown on the 2nd Floor. 
  • Additional structural steel was installed for the new storefront on the elevated walkway.
  • Floor tiles were laid in both restrooms on the 1st Floor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to caulk the exterior concrete panel of the new MEP building.
  • The epoxy floor coating has been applied in the A-Tower storage room and the laundry room.
  • Handrails were installed in the pump room, the switchgear room, and on the roof platform of the new MEP building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The heat exchanger was set in the pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • The contractor demolished half of the old Entergy transformer vault roof.

CSRB EXHAUST UPGRADES:

  • The contractor applied the final coat of paint on the ceiling of the 1st Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor started running reheat lines to the VAV boxes above the Gross Anatomy lab. 
  • They continued installing VAV boxes and supply ductwork for the unit above Oral Pathology. 
  • The contractor pressure tested the manifold systems on both new AHUs. 

DENTAL SCHOOL ATHLETIC FIELDS:

  • Crews continued clearing and grubbing the softball field.
  • They began to add fill to the multi-purpose field.
  • Seven of the catch basin tops (with grates) were installed.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed another 18 light fixtures on the 5th Floor.