Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, FEBRUARY 2, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued priming the stucco in the office area on the 1st Floor.
  • They continued installing the ceramic wall tiles in the 1st Floor restroom near Gravier Street.
  • Workers continued to pull wire to the new elevated emergency life/safety generator.
  • Sheetrock is being installed in the birthing labs on the 2nd Floor.
  • The contractor installed supply air ductwork on the 2nd Floor near the two auditoriums. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the laundry room in Tower A.
  • Workers are installing the main fire sprinkler line on the 1st Floor.   

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the desk in the bookstore.
  • Two metal beams for the mezzanine deck were installed in the pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued removing existing heating hot water pipes and installing the 10 inch supply heating hot water pipe in the basement.
  • Crews continue to remove walls in the elevator pits #7 and #4.
  • The contractor continuing to install conduit on the 2nd Floor. 

CSRB EXHAUST UPGRADE:

  • The contractor placed the first of three coats of plaster on the ceiling of the 1st Floor.
  • They continued installing electrical conduit on the 7th floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running chilled water lines for the AHU above the Gross Anatomy lab.
  • Workers began fabricating the heating hot water lines for the VAV boxes. 

DENTAL SCHOOL STUDENT RECREATIONAL FIELDS:

  • The contractor excavated trenches for storm drain piping connecting the previously installed catch basins.