Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, FEBRUARY 22, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to remove portions of the plaster ceiling on the 2nd Floor bridge area to make way for the structural steel. 
  • Supply and return grilles were installed on the 1st Floor. 
  • Workers continued installing sheetrock near the birthing lab and the 2nd Floor network closet. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to caulk the exterior concrete panels that form the exterior of the new elevated structure.
  • Power for the MDP panel in the C-Tower was transferred to the new switchgear.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began installing heating water piping in the pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • They continued excavating for the electrical duct bank near the generator.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running the reheat lines to the VAV boxes above the Gross Anatomy lab and to the VAV boxes above the Oral Pathology lab. 
  • Crews continued installing VAV boxes and supply ductwork for the unit above Oral Pathology. 

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed an additional 24 light fixtures on the 5th Floor of the Clinic Building.

DENTAL SCHOOL STUDENT ATHLETIC FIELDS:

  • The contractor continued clearing and grading the field.