Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, FEBRUARY 23, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor welded structural steel for the new walkway storefront.  
  • They dropped additional supply and return grilles on the 1st Floor. 
  • Workers continued installing sheetrock near the birthing lab and the 2nd Floor network closet. 
  • The contractor removed the wall paper from the 2nd Floor main corridors.
  • Crews started pulling data wires for the 1st Floor offices. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor began pulling the feeder for the MDP-2 panel in the B Tower.
  • They ran the water line for the fire pump on the second level.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the temporary wiring for the UPS in preparation for Saturday’s power transfer.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • The underground storm drain line near the loading dock area was installed.
  • The man hole for the electrical duct bank near the generator was installed.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running the reheat lines to the VAV boxes above the Gross Anatomy lab.
  • The supply ductwork and fire dampers for the unit above Oral Pathology were installed.   

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • Another 18 light fixtures were installed on the 5th Floor of the Clinic Building.

DENTAL SCHOOL STUDENT ATHLETIC FIELDS:

  • The contractor continued adding new soil to the softball outfield,
  • They began placing red clay for the softball infield.