Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, FEBRUARY 24, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor welded additional structural steel for the new walkway storefront.  
  • Sheetrock was installed around the debriefing rooms on the 2nd Floor.   
  • Workers removed additional wall paper from the 2nd Floor main corridors.
  • Network wiring is being pulled for the 1st Floor offices. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued pulling the feeder for the MDP-2 panel in the B-Tower.
  • They continued running water line for the new fire pump in the elevated structure.
  • Crews are caulking the interior sides of the precast concrete panels that form the walls of the elevated structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed ceiling grid in the back of the house areas. 

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • Workers continued installing the underground storm drain line near the loading dock area.
  • They back filled the man hole for the electrical duct bank near the generator.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running the reheat lines to the VAV boxes above the Gross Anatomy lab and Oral Pathology.
  • Supply ductwork and fire dampers were installed for the AHU above Oral Pathology.   

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • Another 24 light fixtures were installed on the 5th Floor of the Clinic Building.