Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, FEBRUARY 28, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding structural steel for the new walkway storefront entrance.  
  • Workers continued to remove the wall paper from the 2nd Floor main corridors.
  • They started taping and floating the walls on the 2nd Floor near the new auditorium. 
  • Crews continued pulling data wires for the 1st Floor offices. 
  • The contractor sand blasted the floors of 1st Floor offices in preparation for applying an epoxy coating. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor completed pulling feeder and the terminations for the MDP-2 panel for B-Tower.  The panel is now being energized by the new switchgear.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor transferred the power for the UPS to the new switchgear. 
  • Steel columns were erected in the 2nd Floor pump room.
  • The contractor continued to install ceiling grid on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • Steel rebar was installed in the elevator shaft wall forms in the basement.
  • The contractor encased underground electrical conduits with concrete and continued to trench next to the existing generator.

CSRB EXHAUST UPGRADE:

  • The contractor installed a temporary partition in the corridor of the 1st Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running the heating hot water riser to the VAVs near the Gross Anatomy and Oral Pathology labs.       

DENTAL SCHOOL EXTERIOR WATERPROOFING:

  • The contractor started constructing overhead protection at the exterior entrance on the west side of the clinic building.

DS ATHLETIC FIELDS

  • The contractor continued grading the softball outfield.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed another 15 light fixtures on the 5th Floor.
  • They removed 9 fixtures on the 3rd Floor in preparation for the Wet Labs project.