ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing structural steel for the new entryway storefront on the 2nd Floor.
  • Crews ran chilled water lies for the AHU on the 2nd Floor near the existing auditoriums. 
  • The contractor continued painting the 1st floor office areas near Bolivar St.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor pulled wires from the 1st Floor electrical closet to the new 3rd Floor electrical panel for the stoves in Tower C. Temporary power has been provided for Tower C stoves to allow the permanent power to be moved to the new switchgear.   

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor transferred the power for the emergency lighting on the 7th and 8th Floors to the new switchgear.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chill water piping in the basement.
  • The excavation in the loading dock area continued.
  • Workers started installing conduits in Room 309. 

CSRB EXHAUST UPGRADE:

  • The contractor applied the 3rd and final coat of plaster on the 1st Floor ceiling.
  • Floor penetrations were cut in Rooms 630A and 533A.

DENTAL SCHOOL AHU REPLACEMENT:

  • Crews continued fabricating heating hot water lines for the VAV boxes. 
  • The contractor started fabricating the chilled water riser.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed an additional 20 light fixtures on the 7th Floor of the Clinic Building.