Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MARCH 10, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing framing for the 2nd Floor corridor along the MEB loading dock side of the building. 
  • Additional structural steel was welded in place for the new doorway near the MEB loading dock side. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the heat tracer for the domestic water and fire water pipe on the 1st Floor.
  • Crews continued installing the electrical feeder for the MDP-X panel serving the emergency lighting.
  • The contractor pressure washed and cleaned the wall and floor in the C-Tower laundry room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor set 3 of 4 heating hot water pumps in place on the mezzanine in the 2nd Floor pump room.
  • The handrails for the stairs at the generator platform were installed.
  • The ceiling grid was installed in Room 104B.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued trenching and installing electrical conduit in the duct bank along the driveway.
  • They continued installing steel rebar for the passenger elevator shaft in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor removed the plaster ceiling in the corridor adjacent to the cage washer on the 1st Floor.
  • Crews continued installing the temporary exhaust work.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor ran re-heat lines to the VAV boxes near the Oral Pathology labs. 
    • They have completed 3 of 15 boxes near Oral Pathology. 

  • The contractor insulated the piping above the Oral Pathology and Gross Anatomy labs and started insulating the ductwork above the Oral Pathology lab. 

DENTAL SCHOOL BUILDING EXTERIOR WATERPROOFING:

  • The contractor continued pressure washing the exterior wall on the east side of the Clinic Building and the north side of the Admin Building.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor replaced 42 lights in the 3rd Floor clinic area.

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor dug all 25 holes for the new lighting and set the timber pilings for all the new light pole bases.
  • They constructed reinforcing steel cages and formwork for 12 of the light pole bases.