Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MARCH 28, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing three 4-inch standby power conduits and began mounting the electrical box on the exterior of the building.  
  • Crews continued welding structural steel below the walkway along the Gravier Street side of the building. 
  • They continued installing thermostats on the 2nd Floor.
  • The contractor continued installing glass partitions in the 1st Floor offices. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the exterior precast panels and the column on the 1st Floor of the new addition.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heat exchanger piping.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor encased the last section of underground electrical duct bank in concrete near the generator.
  • The contractor continued welding and installing 8-inch chilled water pipes in the basement.

CEB COVERED WALKWAY:

  • The contractor is installing the metal roof panels and flashing on the section of covered walkway closest to the District Energy Garage.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor completed insulating heating water lines near the Oral Pathology lab and started insulating heating water lines near Gross Anatomy.  \
  • Workers continued running control wires for the units near Oral Pathology and Gross Anatomy.   
  • The electrical contractor continued pulling new electrical wire for both units in the penthouse.

DENTAL CAMPUS STUDENT ATHLETIC FIELDS:

  • The contractor applied hydro seed to the newly graded athletic fields.

 DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor replaced 10 light fixtures with new high-efficiency fixtures on the 4th Floor.

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor continued installing direct-buried electrical conduit between light poles and demolished pole bases #21 and #22 that were rejected last week.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued pressure washing the 2nd and 3rd bay on the south side of the Clinic building.
  • They began removing existing caulk on the cross-over section between the Clinic & Administration buildings.