ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing a new electrical box on the exterior of the building.   
  • Crews continued welding structural steel below the walkway along the Gravier Street side of the building. 
  • Control wires were run to the VAVs on the 1st Floor. 
  • The contractor continued installing glass partitions in 1st Floor offices.
  • They painted door frames on the 1st and 2nd Floors.
  • The contractor installed ceiling grid on the 2nd Floor in the Gravier Street corridor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 6 new doors on the 1st Floor of the Residence Hall.

RESOURCE CENTER PRMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heat exchanger piping.
  • Workers began shot-blasting the 1st Floor receiving area in preparation for applying the epoxy floor covering.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor backfilled the electrical duct bank near the generator.

  • They continued welding and installing 8-inch chilled water pipes in the basement.

CEB COVERED WALKWAY:

  • The contractor finished installing the metal roof panels and flashing on the section of covered walkway closest to the District Energy Garage.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor finished insulating the new heating water lines near the Gross Anatomy lab. 
  • They continued installing control wires for the units near Oral Pathology and Gross Anatomy.   
  • The electrical contractor continued installing new electrical wire for the 2nd of 2 units in the penthouse.
  • The contractor replaced the heating hot water riser on the 5th Floor, B side. 

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor replaced 14 light fixtures on the 3rd Floor with high-efficiency fixtures.

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor began wiring the new light poles.
  • They drove new pilings for the bases that will support light poles #21, #22 and #24.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued pressure washing from the 5th Floor upward on the south side of the Clinic Bldg.
  • Workers installed new caulk on the cross-over section between the Clinic and the Administration buildings.