MONDAY, MARCH 7, 2011

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed vibration isolators on 3 heating water pump pads.
  • Workers removed the gypsum board ceiling from the housekeeping closet on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued trenching and installing underground electrical conduit in the driveway of the lakeside lot.
  • They created floor penetrations for electrical conduit in Rooms 730, 627, 523, and 431.

CSRB EXHAUST UPGRADE:

  • The contractor continued installing temporary ductwork on the 1st Floor.
  • Crews removed the insulation from the existing ductwork.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor insulated the heating hot water and chilled water lines for the AHU that serves Oral Pathology.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor replaced 16 lights in the 3rd Floor clinic area.

DENTAL SCHOOL EXTERIOR WATERPROOFING:

  • The contractor cleaned a 20-foot section of the Clinic Building directly above the loading dock and a 50-foot section of the Administration Building on the Florida Ave. side.

DENTAL SCHOOL PARKING LOT LIGHTING:

  • The contractor delivered pilings, sonitubes and light poles to the site.