Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, APRIL 14, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor is priming the floor in the 1st floor offices near Bolivar Street.  
  • Conduit for emergency circuits was run near the 2nd Floor pump room. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing louvers on the roof level of the new elevated mechanical/electrical/plumbing structure.
  • They continued securing and caulking the louvers on the 2nd level of the new structure.
  • The air intake shroud for the emergency generator was installed.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding and installing 8-inch chilled water pipes in the basement.
  • Wire was pulled in the basement for the parking garage exhaust fans, the basement exhaust fan, and the elevator sump pump.
  • The sewer line near the loading dock was connected to the sewer manhole.
  • The contractor started backfilling the old transformer vault site.

CSRB EXHAUST UPGRADE:

  • The contractor installed the testing equipment for the pressure test of the Riser 3 ductwork. 

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued replacing the heating hot water riser on the A-side of the Clinic Bldg. 
    • The 6th floor riser has been replaced.    

  • AHU 8-B is now operational.
  • The contractor started disassembling new AHUs L2A and L3A so they would fit into the freight elevator.   
  • The concrete pads for units L2A and L3A were poured. 
  • The plaster ceiling was removed from the Womens restroom on the 3rd Floor of the Administration Bldg. 
  • Crews continued removing asbestos ductwork from the ceiling in the study rooms of the Library.
  • They completed removing asbestos ductwork in the bookstore and 3rd Floor elevator lobby.    

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing existing caulk and installed new caulk on the east side of both the Clinic and Administration Buildings.

DENTAL CAMPUS PARKING LOT LIGHTING: