Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, APRIL 25, 2011

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the interior CMU wall in the generator room on the 2nd level of the new elevated structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting and installed door hardware on the 1st Floor exterior doors.
  • Crews continued installing the shaft wall in the fire pump room.
  • They began installing the piping for the plant heating water pump manifold.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding and installing 8-inch chilled water line in the basement.
  • Workers backfilled the sewer line near the loading dock and backfilled around the transformer vault.
  • The contractor continued removing existing electrical conduits in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor continued installing the new ceiling supports in the 1st Floor corridor.
  • Exit signs were installed in the 1st Floor corridor.
  • The contractor began rough-in acid waste piping on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor installed 9 fixtures on the 8th Floor and installed ceiling grid in Room 8341. 
  • The A-side riser was pressure tested.
  • The contractor completed installing spiral ductwork for unit 8A on the 8th Floor.
  • Crews started demolishing the two remaining AHUs in the penthouse of the Clinic Building.     
  • The asbestos contractor removed ductwork at the unit in the Clinic penthouse.   
  • The contractor continued running chilled water lines for AHUs L2A and L3A in the Administration Building. 

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor continued installing contactors in the electrical panel at the Moss St entrance to the parking area.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing existing caulk and installed new caulk on the north and south side of the Clinic Building and on the south side of the Administration Building.