Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MAY 12, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued roughing in the med gas system for the 2nd Floor simulation rooms. 
  • They continued installing the metal track for the wood panel system on the 2nd Floor.  
  • Toilet partitions were installed in restrooms on the 2nd Floor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor painted the doors and doorframes on the 1st Floor.
  • Smoke detectors were installed on 2nd Floor of the new structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor placed two concrete pads for the domestic hot water pumps in the 2nd Floor pump room.
  • They continued installing steel stairs in the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical wires on the 3rd Floor and erecting forms for the elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor cut the two roof penetrations for Exhaust System #3.
  • They relocated fan controls for Exhaust Systems #2 and #3.

CEB COVERED WALKWAY:

  • The contractor completed installing the drip flashing and snap-on seam strips on canopy A at the Claiborne Street entrance to the District Energy Garage.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the rectangular supply ductwork and fresh air ductwork for unit 8A in the Clinic Building.     
  • They continued installing heating water lines for units 8D.  
  • The contractor continued installing the transitions between the VAVs and the spiral ductwork for both units; 8A and 8D.
  • Crews continued installing thermostats and ran control wires back to VAVs for both units.  
  • The contractor set both VFDs and started pulling wire for unit 8A. 
  • The reheat lines in the Administration Building were pressure tested and passed.      

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued work on the north and east side of the Clinic Building and on the south side of the Administration Building.

DENTAL CAMPUS PARKING LOT LIGHTING PROJECT:

  • The contractor installed bolt covers.